From DumpLeader website you can free download part of DumpLeader's latest Microsoft certification 70-178 exam practice questions and answers as a free try, and it will not let you down. DumpLeader latest Microsoft certification 70-178 exam practice questions and answers and real exam questions is very close. You may have also seen on other sites related training materials, but will find their Source DumpLeader of you carefully compare. The DumpLeader provide more comprehensive information, including the current exam questions, with their wealth of experience and knowledge by DumpLeader team of experts to come up against Microsoft certification 70-178 exam.
Are you still worrying about how to safely pass Microsoft certification 70-178 exams? Do you have thought to select a specific training? Choosing a good training can effectively help you quickly consolidate a lot of IT knowledge, so you can be well ready for Microsoft certification 70-178 exam. DumpLeader's expert team used their experience and knowledge unremitting efforts to do research of the previous years exam, and finally have developed the best pertinence training program about Microsoft certification 70-178 exam. Our training program can effectively help you have a good preparation for Microsoft certification 70-178 exam. DumpLeader's training program will be your best choice.
In recent, DumpLeader began to provide you with the latest exam dumps about IT certification test, such as Microsoft 70-178 certification dumps are developed based on the latest IT certification exam. DumpLeader Microsoft 70-178 certification training dumps will tell you the latest news about the exam. The changes of the exam outline and those new questions that may appear are included in our dumps. So if you want to attend IT certification exam, you'd better make the best of DumpLeader questions and answers. Only in this way can you prepare well for the exam.
DumpLeader Microsoft 70-178 exam training materials praised by the majority of candidates is not a recent thing. This shows DumpLeader Microsoft 70-178 exam training materials can indeed help the candidates to pass the exam. Compared to other questions providers, DumpLeader Microsoft 70-178 exam training materials have been far ahead. uestions broad consumer recognition and reputation, it has gained a public praise. If you want to participate in the Microsoft 70-178 exam, quickly into DumpLeader website, I believe you will get what you want. If you miss you will regret, if you want to become a professional IT expert, then quickly add it to cart.
In recent years, fierce competition agitates the forwarding IT industry in the world. And IT certification has become a necessity. If you want to get a good improvement in your career, The method that using the DumpLeader’s Microsoft 70-178 exam training materials to obtain a certificate is very feasible. Our exam materials are including all the questions which the exam required. So the materials will be able to help you to pass the exam.
Exam Code: 70-178
Exam Name: Microsoft (Microsoft Project 2010, Managing Projects)
One year free update, No help, Full refund!
Total Q&A: 70 Questions and Answers
Last Update: 2013-12-22
IT certification candidates are mostly working people. Therefore, most of the candidates did not have so much time to prepare for the exam. But they need a lot of time to participate in the certification exam training courses. This will not only lead to a waste of training costs, more importantly, the candidates wasted valuable time. Here, I recommend a good learning materials website. Some of the test data on the site is free, but more importantly is that it provides a realistic simulation exercises that can help you to pass the Microsoft 70-178 exam. DumpLeader Microsoft 70-178 exammaterials can not only help you save a lot of time. but also allows you to pass the exam successfully. So you have no reason not to choose it.
70-178 Free Demo Download: http://www.dumpleader.com/70-178_exam.html
NO.1 A section of your project contains only a summary task along with four subtasks and a milestone. You
discover that the section is located in the incorrect phase and has the incorrect Work Breakdown
Structure (WBS) numbering. You need to move the section to another phase of the project. You also need
to ensure that the section reflects the correct WBS numbering. What should you do?
A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task.
Answer: C
Microsoft certification 70-178 70-178 test 70-178
NO.2 You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.
B. On the Format tab, select Summary Tasks.
C. On the Format tab, select Project Summary Task.
D. Insert a new Summary Task.
Answer: C
Microsoft 70-178 test answers 70-178 questions 70-178 certification 70-178
NO.3 You manage a project that specifies all constraint types to As Soon As Possible. You discover that one
of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted
finish date on the default Gantt chart. What should you modify in the Task Information window?
A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box.
Answer: A
Microsoft 70-178 exam prep 70-178 exam 70-178 dumps 70-178
NO.4 You need to set the default constraint type for all new tasks to As Late As Possible. What should you
do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop-down list box, select Project Finish
Date.
Answer: D
Microsoft pdf 70-178 70-178 70-178 test questions 70-178 70-178
NO.5 You have a Project 2010 schedule that contains the following tasks:
Inactive tasks
Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are
created. What should you do.?
A. Change all inactive tasks to active tasks.
B. Change all tasks that contain strikethrough font to tasks that include normal font.
C. Change all manually scheduled summary tasks to automatic scheduling.
D. Change all manually scheduled tasks to automatic scheduling.
Answer: C
Microsoft exam simulations 70-178 70-178 70-178
NO.6 You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You
highlight the four tasks. Which command should you use?
A. Outdent
B. Fill Down
C. Insert Summary
D. Move Task
Answer: C
Microsoft 70-178 Braindumps 70-178 70-178 70-178 test answers
NO.7 The first major phase of your project is scheduled for a duration of 45 days. However, you do not have
task information for other phases. You need to indicate that the duration of the entire project is 200 days.
What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Answer: C
Microsoft 70-178 exam 70-178
NO.8 You manage a project according to the schedule as shown in the exhibit.
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A. Create a task dependency from Task 4 to Task 6.
B. Set Task 4 as critical.
C. Add a 1 day lead to Task 4.
D. Set Task 4 as manually scheduled.
Answer: D
Microsoft 70-178 test 70-178 study guide
NO.9 The project you manage has only part-time resources. The part-time resources work four hours a day
from Wednesday through Saturday. You need to create a new calendar and set the calendar as the
default for your project. Which two actions should you perform? Each correct answer presents part of the
solution.
A. Select the part-time calendar from the Change Working Time window.
B. Set the calendar type to part-time for all tasks.
C. Select the part-time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box.
Answer: CD
Microsoft Braindumps 70-178 70-178
NO.10 You manage several projects. Each project has shared resources and work distribution. You need to
ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on
each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view
to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level
Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Answer: C
Microsoft 70-178 demo 70-178 answers real questions 70-178 demo
DumpLeader offer the latest 74-353 exam material and high-quality 642-447 pdf questions & answers. Our LOT-406 VCE testing engine and 74-324 study guide can help you pass the real exam. High-quality 700-104 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.